Friday, October 22, 2010

Blue-Digestor Reconstruction on 22/10/10 (Friday), 9am-3pm

All in all, we dismantled prototype 1 (blue) & transported it back to ensure engineering. Did purchasing again for blue-D valves and fittings; PVC Cement & Primer; Grey-D aerobic stage bends


Sort of freak accident - the soil softened and barricade collapsed over our lorry - KH & Brenda almost died, click on image to enlarge:





Brenda to call on sat (23/10/10) :
  • Dr Han - Blue-D top (air tightness) + bottom (leakage issues)
  • Cancel Vac truck appointment on monday
  • Taiko for Drums x3
  • Book Vac truck for Wednesday
  • Book transportation (forklift) for Grey-Digestor for Wednesday

Plan for 25-31 October 2010 (S2 week 1):

Mon:      KH to go ensure to finalise Grey-Digestor design issues with Murugan/Kannan.
Tues:      None; allow ensure to construct Grey-D according to KH's instructions
Wed:      All 3; Transport Grey-D, Load Orange and Grey-D (noon), buy fittings from sunhee (evenings)
Thurs:    Marc & KH; Blue-D building at ensure
Friday:   Brenda & KH; Blue-D building at ensure
Sat & Sun: May go down to ensure, depending on progress


Due to Blue-D's issues & delays; fyp runs limited to:
  • Orange-D: 3
  • Grey-D: 3
  • Blue-D: 2
Each run is estimated at 14 days; 1st Run to commence on 27 October 2010 (Wednesday).


*** KH to get Drager Tubes & Drager pump ***


Kian How, signing off on 22/10/10, 10.20 pm.